Harbour Update
It’s somewhat confusing but there are two major Harbour projects being discussed at Council and they both get mentioned at next week’s CoW meeting. The first is fixing the harbour walls and breakwaters for a total of $12.8M and the second is rehabilitation of the East Pier (budget estimate for 2024 is $3.6M) – that is, to make it an attractive place. Work on the East Pier rehabilitation cannot start until at least the harbour walls and East Breakwater work is done. The two consultants involved are making presentations: Shoreplan is providing a walls and breakwaters project update which is essentially the same as provided in the Engage Cobourg Survey information and reported here on 29 January – see link… Read complete articleHarbour Update